Well, today is ANZAC day, and obviously there's not much happening on the data centre front - at least nothing physical.
We know some staff and contractors are working behind the scenes finalising the design - aspects such as the exact routes for pipe work & cabling, locking in the initial rack layout, and other stuff like that.
Below is a picture of two thirds of the initial mains supply switchboard. These two sections when assembled are a shade over 5 metres long - they've been built in two parts for shipping.
There's also two UPS output switchboards - one of which is pictured in the second photo (both UPS output boards are identical).
In addition to these, the final build will have 1 general purpose switchboard to run lights and unprotected outlets, 2 boards to feed the air conditioning units, and 8 boards to distribute power to the customer racks.


We know some staff and contractors are working behind the scenes finalising the design - aspects such as the exact routes for pipe work & cabling, locking in the initial rack layout, and other stuff like that.
Below is a picture of two thirds of the initial mains supply switchboard. These two sections when assembled are a shade over 5 metres long - they've been built in two parts for shipping.
There's also two UPS output switchboards - one of which is pictured in the second photo (both UPS output boards are identical).
In addition to these, the final build will have 1 general purpose switchboard to run lights and unprotected outlets, 2 boards to feed the air conditioning units, and 8 boards to distribute power to the customer racks.