The raised floor is now just waiting on floor vents to be installed next week, which will make this project for the contractors complete. All our fire suppression pipe work arrived on-site today and is awaiting installation. Electrical work and air conditioning pipe work has continued today, and will be ongoing next week.
Today our splicing technicians began the process of terminating the fibre into the Tyco FIST-GR2 racks. Each rack, when full, will terminate a total of 432 fibres. Each GR2 rack can hold a total of 13 shelves; each shelf has 6 trays with 12 fibres per tray. This gives a total of 72 fibres per shelf. Yesterday one rack was installed on the main data centre floor, the other in an area next to the UPS room (these areas will both be secured by cages) and both racks are directly bolted to the concrete floor to stop them toppling.

In preparation for termination the cables have to be stripped of their outer sheaths and each tube of fibres (24 tubes with 12 fibres in each tube) has to be laid up to prevent damage. The tubes that will be terminated first have to be cleaned and prepped for splicing.
The prepped fibres will then be spliced on to pigtails. From here, the fibres will be patched to a second GPS shelf. This gives us an extra level of separation from the street cable and provides better control of the in-building patching to customers.
The FIST-GR2 provides excellent cable management within the racks to ensure that things don’t get messy and that even when full, the fibre is always 100% accessible without causing damage or an outage for a customer.
The two street cables enter the building via different paths providing a fully diverse path to and from the DC. It will also be possible to maintain diverse paths to a rack within the DC too.
Today our splicing technicians began the process of terminating the fibre into the Tyco FIST-GR2 racks. Each rack, when full, will terminate a total of 432 fibres. Each GR2 rack can hold a total of 13 shelves; each shelf has 6 trays with 12 fibres per tray. This gives a total of 72 fibres per shelf. Yesterday one rack was installed on the main data centre floor, the other in an area next to the UPS room (these areas will both be secured by cages) and both racks are directly bolted to the concrete floor to stop them toppling.
In preparation for termination the cables have to be stripped of their outer sheaths and each tube of fibres (24 tubes with 12 fibres in each tube) has to be laid up to prevent damage. The tubes that will be terminated first have to be cleaned and prepped for splicing.
The prepped fibres will then be spliced on to pigtails. From here, the fibres will be patched to a second GPS shelf. This gives us an extra level of separation from the street cable and provides better control of the in-building patching to customers.
The FIST-GR2 provides excellent cable management within the racks to ensure that things don’t get messy and that even when full, the fibre is always 100% accessible without causing damage or an outage for a customer.
The two street cables enter the building via different paths providing a fully diverse path to and from the DC. It will also be possible to maintain diverse paths to a rack within the DC too.








Calendar



