Our fire suppression contractors were on-site today working on the pipework for the FM-200 system.

Progress on this, and quite a few other items, has been hampered over recent weeks by limitations being placed upon when we can make noise (even minor tasks like core boring, which make very little noise, have been restricted). Despite this our contractors have done an excellent job of keeping things pretty much on track.
Those paying attention will note that the first batch of racks that were supposed to arrive on Wednesday this week didn't arrive - they're now scheduled to arrive in one batch next Wednesday. The delay has been caused by 3rd party works outside our tenancy that have made deliveries quite difficult. Despite this, it's not expected to cause us any major issues as we can juggle things around to suit.
The flooring itself is now complete, with only the floor vents, cable holes, and access ramps/stairs to be completed.
We'll be cutting out the temporary lighting shortly (left over from the old office fitout) as it's no longer needed. We'll have to be careful though - the two webcams are powered from that circuit :-)
The old smoke detectors and associated wiring will be removed once the VESDA/FM200 system is commissioned, so a lot of legacy roof clutter will be gone for good!
Telstra have already been on-site to look at installing services for our first telehousing customer at DC3. Not surprisingly, they're likely to be the first carrier (after ourselves of course) to deliver a carrier service to a customer in our facility.
The datacentre cleaners are scheduled to come in shortly to do a thorough clean. This involves vacuuming under the floor, wiping under the floor, lifting every floor tile and cleaning the supporting structures, wiping the tiles, the walls, and all the other surfaces. Not an insignificant job!
Progress on this, and quite a few other items, has been hampered over recent weeks by limitations being placed upon when we can make noise (even minor tasks like core boring, which make very little noise, have been restricted). Despite this our contractors have done an excellent job of keeping things pretty much on track.
Those paying attention will note that the first batch of racks that were supposed to arrive on Wednesday this week didn't arrive - they're now scheduled to arrive in one batch next Wednesday. The delay has been caused by 3rd party works outside our tenancy that have made deliveries quite difficult. Despite this, it's not expected to cause us any major issues as we can juggle things around to suit.
The flooring itself is now complete, with only the floor vents, cable holes, and access ramps/stairs to be completed.
We'll be cutting out the temporary lighting shortly (left over from the old office fitout) as it's no longer needed. We'll have to be careful though - the two webcams are powered from that circuit :-)
The old smoke detectors and associated wiring will be removed once the VESDA/FM200 system is commissioned, so a lot of legacy roof clutter will be gone for good!
Telstra have already been on-site to look at installing services for our first telehousing customer at DC3. Not surprisingly, they're likely to be the first carrier (after ourselves of course) to deliver a carrier service to a customer in our facility.
The datacentre cleaners are scheduled to come in shortly to do a thorough clean. This involves vacuuming under the floor, wiping under the floor, lifting every floor tile and cleaning the supporting structures, wiping the tiles, the walls, and all the other surfaces. Not an insignificant job!








Calendar



